Contractor given two months to complete Ruringu Stadium - Capital Sports
Connect with us

Hi, what are you looking for?

The stalled works at Nyeri's Riungu Stadium. Photo/Josphat Kinyua

Headlines

Contractor given two months to complete Ruringu Stadium

NYERI, Kenya, June 30 – Sports Kenya has given a contractor building a sh280 million Ruringu Stadium in Nyeri two months to complete works which has stalled for the last three years.

Speaking Tuesday after touring ongoing works, the team led by Nyeri County Commissioner, Loyford Kibaara, Sports Kenya Director Mwangi Muthee and area MP Wambugu Ngunjiri said that the contactor must finish the works by latest September 30 failure to which he will face sanctions.

Construction of the 15-seater Stadium was launched by President Uhuru Kenyatta on June 2017, but its construction stalled moments after due to nonpayment of the contractor by the government.

However, works started again in May this year after the contractor signed return to work agreement with the ministry of sports and undertook to complete remaining works.

During today’s tour the contractor Sam Mwaniki was taken to task by officials due to the delay and at one point he exchanged bitter words with Kibaara.

“I want to know why this work is not complete, yet the government does not owe you a cent, tell us when you will be through and stop lying to us,” said Kibaara.

On his part, Muthee said that an officer will be deployed on the site to ensure that work is done day and night for the stadium to be complete in those two months.

“We have agreed with the contractor that each week a certain portion of work must be done, this will be under supervision of works officer and offices from County Commissioner office this stadium must be done on time,” said Muthee.

Wambugu said that the stadium must be complete to spur sport tourism in the area owing to the stadium historic importance and the fact that it’s a high-altitude training facility.

The contactor said that he has no problem completing the remaining sixty percent of works but stated that he is getting part of payment.

Advertisement. Scroll to continue reading.

“Nyerians must understand that we have not received full payment as implied we are getting payments of work done but I have no problem now and I will complete building this facility on time,” revealed Mwaniki.

-By Josphat Kinyua

Advertisement

More on Capital Sports

Football

NAIROBI, Kenya, Oct 27 – DStv and GOtv subscribers are in for a treat of the world’s best football this week as the 2020-21...

Football

NAIROBI, Kenya, May 25 – There is light at the end of the tunnel. After failed promises over the last three years since its...

Football

NAIROBI, Kenya, Sep 6 – Gentrix Shikangwa scored with two minutes left as Vihiga Queens sailed to the final of the CECAFA regional qualifiers...

NFL

NAIROBI, Kenya, Aug 13 – Kenya’s history making Daniel Adongo, the first Kenyan to play in America’s National Football League (NFL), is now living...

© 2024 Capital Digital Media. Capital Group Limited. All Rights Reserved