Connect with us

Hi, what are you looking for?

top

World

British parliament should decamp for £3.9 bn repairs: lawmakers

Scaffolding on top of the Palace of Westminster which houses the Houses of Parliament in central London on September 8, 2016 © AFP / Daniel Leal-Olivas

London, United Kingdom, Sep 8 – British lawmakers should move out of London’s iconic Houses of Parliament for six years while the crumbling building is renovated to avert a crisis, a parliamentary report said Thursday.

Behind its neo-Gothic facades topped by the world-famous Big Ben clock tower, the mother of parliaments has been eroded by air pollution and is overrun with mice, prompting warnings it may have to be permanently abandoned unless urgent renovations are carried out.

After a year of deliberations, the Joint Committee on the Palace of Westminster recommended Thursday that MPs from the House of Commons move into the nearby health ministry building, saying there was a growing risk of a “catastrophic event”.

The House of Lords — the parliament’s upper chamber — should move to the less grandiose surroundings of the nearby Queen Elizabeth II Conference Centre, the committee said, recommending the move take place between 2022 and 2028.

“The Palace of Westminster, a masterpiece of Victorian and medieval architecture and engineering, faces an impending crisis which we cannot responsibly ignore,” said the report.

“It is impossible to say when this will happen, but there is a substantial and growing risk of… a catastrophic event, such as a major fire.

“If both houses fully vacated the palace this would take the least time and would avoid disruption to parliament from construction works,” it concluded.

Although the building had suffered “extensive erosion and water damage”, the report found there was no risk of it collapsing.

– Leaky Roofs –

If lawmakers were to move, the cost of renovations would be around £3.9 billion ($5.2 billion, 4.6 billion euros), compared with £6 billion if the work took place around the parliamentarians.

Advertisement. Scroll to continue reading.

The House of Lords chamber in session at the Houses of Parliament in London on September 5, 2016 © Pool/AFP/File / Kirsty Wigglesworth

Many of the vast building’s roofs are prone to leaks and asbestos is a constant hazard. Even the famous clock tower leans 46 centimetres (18 inches) off the vertical.

Rodents are frequently spotted scurrying around the members’ tea room, while MPs complain of cramped working areas and faulty heating.

Work would also include rewiring and updating the Victorian facilities.

House of Commons Speaker John Bercow warned that parliament might have to move for good within 20 years unless major renovations take place in the next decade.

Lawmakers will have the final decision, with Prime Minister Theresa May yet to back the plans.

“The PM’s view is that we should carefully consider the proposals and will want to hear the views of MPs before deciding on the direction,” said a spokesman from her Downing Street office.

The Houses of Parliament, designed by Charles Barry and Augustus Pugin, were completed in 1870 and are now a UNESCO World Heritage Site.

Although a fire in 1834 destroyed most of the old Palace of Westminster and parts of the Commons had to be rebuilt after World War II due to bomb damage, there are still some areas which date back to the 11th century.

The repair plans are likely to prove controversial, with the British taxpayer footing the huge bill at a time of public spending cuts.

Opposition Labour committee member Chris Bryant insisted that the renovation “is certainly not a vanity project”, and that the building was “part of our national heritage”.

Advertisement. Scroll to continue reading.