Connect with us

Hi, what are you looking for?

top
Wind Power in Morocco/AFP

Kenya

Change in air as Africa’s biggest wind farm set for Kenya

Wind Power in Morocco/AFP

SOUTH HORR, Kenya, Jun 7 – Tumbling down to the jade waters below, the rugged hills around Lake Turkana in northern Kenya are made of boulders and lava stone.

This is a remote, lunar landscape and the site of what will one day be Africa’s largest wind farm.

A consortium of European and African companies is preparing to put up 365 wind turbines in a 165 km2 (64-square-mile) stretch of this desolate area inhabited only by semi-nomadic pastoralist herders.

As yet, there is little sign of the project. The hills appear untouched by humans, except for nine masts set up to measure the wind that surges between the Kulal and Nyiro mountains.

This wind, which rises over Lake Turkana before dying out over the Sahara, blows at an average speed of 11 metres per second and is a dream for any engineer working in wind energy.

“In Turkana, the wind speed and also the consistency provides for optimum conditions for wind power — in fact they are better than North Sea offshore wind power,” said Achim Steiner, executive director of the Nairobi-based United Nations Environment Programme.

“Here you can produce wind power at an interesting cost, without subsidies,” unlike the case in Europe, said Carlo Van Wageningen, chairman of the Lake Turkana Wind Power (LTWP) consortium.

LTWP has entered into a contract to sell the power produced to utility firm Kenya Power over 20 years at a cost of 7.52 euro cents/kwh, a much lower price than that paid for the hydro-electric power mainly used today.

If everything turns out well, the Turkana project will be a poster child for sustainable development — the notion that growth can be clean and improve life for the poor. Green groups, businesses and politicians are heading to Rio de Janeiro this month to give the doctrine a push, culminating with a UN summit on June 20-22.

— A camp tent blowing away —

Advertisement. Scroll to continue reading.

The project all started when a Dutchman had to continually struggle to stop his tent getting blown away by the wind during a camping trip to Turkana.

He recounted the experience to a compatriot who specialised in wind energy — and so set the ball rolling on seven years of studies, financial negotiations and setbacks.

The financial backing is now secured, with only risk guarantees from the World Bank lending agencies Ida and Miga remaining to be finalised.

Once the green light is given on those, potentially by this August, then work can begin.

“All the contracts are in place. We’re ready to start,” Van Wageningen said.

The first step will be to build 204 kilometres (126 miles) of road to allow lorries to make the 12,000 round-trips needed to deliver all the necessary materials from Mombasa at one end of the country to Turkana at the other.

The turbines will be erected in one year, at the rate of one per day, and the first kilowatts of electricity should be delivered to the grid by the end of 2013.

By the time it reaches its full capacity, penciled in for the end of 2014, the site will produce 300 MW of electricity.

“We will represent about 20% of the national electricity production” said Chris Staubo, a director at LTWP.

Advertisement. Scroll to continue reading.

The project will cost 585 million euros ($728 million), plus an additional 142 million euros needed to build 428 km of high tension power lines linking the wind farm with the country’s main power transformer at Suswa.

The African Development Bank is the lead arranger behind a loan covering 70 percent of the enterprise.

The Turkana project is dramatically more ambitious than Africa’s current largest wind farm, located at Melloussa in Morocco with 165 turbines and a capacity of 140 MW.

“Kenya is in the midst of pioneering the largest wind power project in Africa and I think, embedded in a green policy of national development,” added UNEP’s Steiner.

“It demonstrates precisely that there is an enormous potential for green energy to succeed in Africa, and indeed these projects need to be supported because they break new ground,” he added.

The arrival of the 48-metre tall wind turbines will radically change the lives of 528 pastoralists — from the Turkana, Samburu, Rendille, Gabra and El Molo tribes — who are still without electricity, running water, telephones, television and even money, relying instead on bartering goods.

LTWP have promised them a 20-year development plan of approximately 1.5 million euros each year. But they will first temporarily have to shift their village of Sirima to clear the way for the future supply road.

Despite this, local member of parliament Joseph Lekuton said that he was “100% with” the project “since the beginning and until the end”.

“The animals will graze where they used to graze,” he said, pointing out that the wind farm would not be fenced off.

Advertisement. Scroll to continue reading.

For village elder Simon Ekitoe “there will be some good things and some less good things.”

He fears that the arrival of outsiders will bring “new diseases, forced marriages” and that “the women in the village will spurn their traditional dress.”

But for grandmother Agnes Ngare, with dozens of rings of red beads around her neck and metal earrings dangling from her ears, there is not so much to be worried about.

“I dream that my children and grandchildren will go to school and be able to choose how they want to live their lives,” she said.

“If electricity arrives, that would change my life as I could listen to radio, have a mobile phone and watch television,” she laughed.

About The Author

Comments
Advertisement

More on Capital News